Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
This SAE Recommended Practice defines the test conditions, procedures, and minimum design requirements for nominal 6, 12, and 24 V warning lamp alternating flashers used in surface vehicles. The standard ensures that flashers perform reliably under various electrical and environmental conditions, promoting safety and consistency in vehicle lighting systems.
Testing is conducted in accordance with SAE J823 and covers the following areas:
| Parameter | Requirement |
|---|---|
| Start Time (average of three) | ≤ 1.5 s |
| Start Time (any single measurement) | ≤ 2.0 s |
| Voltage Drop (average) | ≤ 0.5 V |
| Voltage Drop (any reading) | ≤ 0.8 V |
| Flash Rate | 60 – 120 flashes/min |
| Duty Cycle (each load terminal) | 30% – 75% |
| Total Duty Cycle (both terminals combined) | 90% – 110% |
| Extreme Temperature – Start Time | ≤ 5 s |
| Extreme Temperature – Flash Rate | 30 – 150 flashes/min |
Designing an alternating flasher to meet SAE J1054 requires careful attention to the following:
What are the nominal voltage levels and corresponding test voltages?
For a 12 V nominal system, the baseline test voltage is 12.8 V at the bulb. The standard also specifies tests at 12.0 V, 15.0 V, 11.0 V, and 14.0 V to cover voltage extremes. For 6 V systems, these values are halved (6.4 V, 6.0 V, 7.5 V, 5.5 V, 7.0 V); for 24 V systems they are doubled (25.6 V, 24.0 V, 30.0 V, 22.0 V, 28.0 V).
How is start time defined and measured?
Start time is the duration from the moment voltage is applied to the flasher until both load circuits have completed one full cycle (energized and de-energized). Three start measurements are taken at 24 °C with at least five minutes of cooling between each. The average must not exceed 1.5 s, and no single measurement may exceed 2.0 s.
What are the allowed flash rate and duty cycle?
Each load terminal must flash at a rate between 60 and 120 flashes per minute. The percentage of time that current is on (duty cycle) must be between 30% and 75% for each terminal, and the sum of both terminals’ duty cycles must fall between 90% and 110%.
What does the durability test involve?
The flasher first undergoes 100 hours of intermittent operation (15 seconds on, 15 seconds off) followed by 50 hours of continuous flashing. The test voltage is 13.0 V (6.5 V for 6 V, 26.0 V for 24 V) at 24 °C ambient. After the test, the flasher must still meet the start time, voltage drop, flash rate, and duty cycle requirements under standard conditions.