Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
IEC 62381 is the international standard that defines the requirements and procedures for Factory Acceptance Tests (FAT), Site Acceptance Tests (SAT), and Site Integration Tests (SIT) applied to automation systems in the process industry. Published in its second edition in 2012, this standard provides a structured framework for verifying that automation systems meet their specified requirements before, during, and after installation.
The standard covers all types of process automation systems including distributed control systems (DCS), safety instrumented systems (SIS), programmable logic controllers (PLC), and supervisory control and data acquisition (SCADA) systems. It applies to both hardware and software aspects of the automation solution.
A key principle of IEC 62381 is the progressive verification approach: FAT validates the system at the vendor site before shipping, SAT confirms correct installation and basic functionality at the plant site, and SIT verifies that the automation system integrates correctly with other plant systems and processes.
| Test Phase | Location | Primary Objective | Participants |
|---|---|---|---|
| FAT | Vendor facility | Verify system meets functional and performance specs before shipment | Vendor, owner/contractor |
| SAT | Plant site | Confirm installation, cabling, and basic operation after delivery | Owner, contractor, vendor support |
| SIT | Plant site | Validate integration with field devices, third-party systems, and plant network | Owner, integration team, vendor |
The Factory Acceptance Test (FAT) is the first major verification milestone. Performed at the vendor facility before equipment shipment, the FAT demonstrates that the automation system conforms to the functional design specification (FDS), hardware design, and software requirements.
IEC 62381 requires comprehensive test documentation including a FAT test plan that defines test objectives, test cases, acceptance criteria, and pass/fail conditions. The test plan should cover: hardware configuration verification, I/O signal integrity, control logic performance, alarm and event handling, HMI functionality, communication interfaces, and system response times.
The standard specifies that FAT should simulate plant operating conditions as closely as possible. This includes testing normal operation, startup and shutdown sequences, alarm conditions, and failure modes. Any deviations discovered during FAT must be documented as non-conformance reports (NCR) with agreed resolution plans.
A critical aspect often underestimated is the software functionality FAT. IEC 62381 requires testing of all control strategies, interlock logic, sequence controls, and regulatory control loops against the approved design documents.
Experienced automation engineers recommend preparing a FAT checklist organized by system function rather than by hardware. This functional approach ensures that cross-system interactions are tested, not just individual components. Include at least 20% margin in the FAT schedule for regression testing after defect fixes.
Site Acceptance Test (SAT) begins after the automation system is delivered and installed at the plant. While FAT confirmed the system works in a controlled environment, SAT verifies that the system functions correctly after transportation, handling, and installation.
Site Integration Test (SIT) is the final and most comprehensive test phase. SIT validates that the automation system integrates correctly with all plant subsystems including field instruments, motor control centers, fire and gas systems, emergency shutdown systems, and plant information networks.
IEC 62381 outlines specific integration test categories: communication protocol verification (Profibus, Modbus, Foundation Fieldbus, etc.), data flow between subsystems, time synchronization accuracy, network load testing, and cybersecurity interface validation. SIT must also verify system performance under realistic plant operating scenarios.
The standard recommends maintaining a traceability matrix linking test cases back to requirements throughout all three test phases, ensuring complete coverage and clear evidence for regulatory compliance.
| Test Parameter | FAT | SAT | SIT |
|---|---|---|---|
| Environment | Lab/simulated | As-installed | Integrated plant |
| Duration | 1-4 weeks | 1-2 weeks | 2-8 weeks |
| Defect Cost Multiplier | 1x | 3-5x | 8-15x |
| Coverage Focus | Functional completeness | Installation correctness | System interoperability |
FAT is performed at the vendor facility before shipment to verify the system meets design specifications. SAT is performed at the plant site after installation to confirm the system survived transport and was installed correctly.
Yes. The standard covers both hardware and software aspects. For software-only systems, FAT focuses on functional correctness and performance, while SIT validates integration with other software systems and databases.
All deviations must be documented as Non-Conformance Reports (NCR) with a unique identifier, description, root cause analysis, corrective action plan, and re-test criteria. The NCR log should be maintained and reviewed daily during FAT.
While they can be combined for small projects, IEC 62381 recommends keeping them separate for medium to large projects. SAT focuses on installation verification, while SIT validates system integration.