Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
Physical Address
304 North Cardinal St.
Dorchester Center, MA 02124
IEC 62116:2014 (2nd edition) specifies a standardized test procedure for evaluating the performance of automatic islanding prevention measures in single or multi-phase utility-interactive PV inverters. Islanding occurs when a portion of the utility grid containing both load and generation becomes isolated from the main grid but continues to operate. This condition is hazardous because it can energize lines thought to be dead, create out-of-synchronization reclosure, and damage equipment through uncontrolled voltage and frequency.
The test procedure quantifies the “run-on time” (tR) — the interval between grid disconnection and cessation of inverter output. Inverters meeting the requirements are considered “non-islanding” as defined in IEC 61727.
| Parameter | Test Condition A (100 %) | Test Condition B (50-66 %) | Test Condition C (25-33 %) |
|---|---|---|---|
| Active power output | 100 % rated | 50-66 % rated | 25-33 % rated |
| Quality factor (Qf) | 1 ± 0.1 | 1 ± 0.1 | 1 ± 0.1 |
| Load imbalance (real) | ±2 %, ±5 % | N/A | N/A |
| Load imbalance (reactive) | ±1 %, ±3 % | ±1 % | ±1 % |
The test circuit (Figure 1 of the standard) consists of an AC power source simulating the utility grid, a DC power source simulating the PV array (or a PV array simulator), the equipment under test (EUT — the inverter), and a parallel RLC load bank. A switch (S1) connects/disconnects the grid simulator, and measurement instruments capture voltage, current, frequency, and timing parameters.
The 2014 edition expanded the acceptable DC source types and clarified their specifications. A PV array simulator is the preferred option, but an actual PV array or a current/voltage limited DC power supply with series resistance may also be used. The critical requirement is that the DC source does not limit the maximum EUT input current during transient islanding conditions.
| DC Source Type | Advantages | Limitations |
|---|---|---|
| PV array simulator | Programmable I-V curve, high accuracy, repeatable | High cost, complex setup |
| Actual PV array | Most realistic, no simulator artifacts | Weather dependent, not repeatable |
| DC supply with series R | Simple, low cost | Limited realism, poor transient response |
A critical concept in IEC 62116 is the Quality Factor (Qf) of the test load. Qf is defined as the ratio of reactive power to active power in the resonant circuit:
Qf = R × √(C/L) = (1/P) × √(QL × QC)
Higher Qf makes islanding harder to detect because the resonant load better sustains the voltage and frequency within normal operating ranges. The standard specifies Qf = 1 ± 0.1 for all test conditions.
The standard defines three test conditions at different power output levels, each with specific load imbalance scenarios. The EUT must be tested at each condition multiple times (typically 10 runs per condition). The pass/fail criterion is based on the measured run-on time (tR) — the time from grid disconnection to output cessation.
The acceptance criteria require that the inverter cease output within 2 seconds for all test runs, with no sustained islanding condition observed. Some national standards may specify more stringent limits (e.g., 0.2 seconds per IEEE 1547 in the United States).
The standard specifies detailed documentation requirements including: manufacturer-specified inverter trip settings (voltage and frequency thresholds), complete test results for all conditions and runs, test equipment specifications and calibration dates, ambient conditions during testing, and any anomalies observed.
Key changes include: updated DC power source specifications (5.2), modified AC load specifications (5.4), revised test condition power levels (from 90%/10% to 75%/20% for certain parameters), updated voltage and frequency trip settings reference to national standards, and improved documentation templates.
Yes, Clause 6 specifically addresses testing of single or multi-phase inverters. For multi-phase inverters, the load imbalance conditions in Tables 6 and 7 must be applied to create realistic test scenarios.
The quality factor (Qf) represents how sharply the load resonates at the grid frequency. A higher Qf makes islanding harder to detect. Qf = 1 represents a realistic worst case for typical installations.
The standard was developed for PV inverters but the scope notes that it may be applied to other utility-interconnected systems (including battery inverters and microturbines) with appropriate technical review. The fundamental test methodology is applicable, but some parameters may need adjustment.