ASME SPPE 1A-1991 — Quality Assurance and Certification of Safety and Pollution Prevention Equipment Used in Offshore Oil and Gas Operations (Addenda 1A)

🐬 ASME SPPE 1A-1991 is the first Addenda to ASME SPPE-1-1991, Quality Assurance and Certification of Safety and Pollution Prevention Equipment (SPPE) Used in Offshore Oil and Gas Operations. It was issued on November 1, 1991, and approved by the American National Standards Institute (ANSI) on September 3, 1991. Like all SPPE addenda, it takes the form of replacement pages that incorporate revisions directly into the base document. The focus of this first addenda is the establishment, documentation, evaluation, and continuing compliance of a manufacturer’s Quality Assurance Program — the backbone of third-party certification for SPPE products.

💡 An addenda is not a standalone standard: wherever the affected text carries a margin note (a), that change was introduced by this addenda.

1. What This Addenda Changed 📌

Four page locations were revised, inserted, or added, as summarized below:

Page Location Change
Page 5 OE-3120 Revised — documentation requirements for the Quality Assurance Program
Page 9 OE-4215 Revised — inspection, test, and operating status identification
Page 13 Appendix I Revised — listings for API 14B and API 14D updated
Pages 28.1–28.3 Appendix VII Added — Inquiries 90-3, 90-4, 91-1, 91-2, and 91-3

All revisions are flagged by the margin note (a). The 1991 edition text and all pages not replaced remain in effect. ASME recommends retaining the addenda title and copyright pages, this summary page, and all replaced pages for reference and traceability.

2. Core Certification Requirements 🔧

SPPE-1 establishes a third-party certification mechanism built around the Certificate of Authorization and the OCS Symbol. This addenda refines several elements of that mechanism:

  • Applicants: An applicant must establish a Quality Assurance Program for assuring the quality of the parts/SPPE it proposes to produce, and must request evaluation on forms designated by the Society.
  • Quality Assurance Manual: The Program must be documented in a Quality Assurance Manual, which becomes the basis for demonstrating compliance. Once accepted and a Certificate is issued, a controlled copy remains on file with the Society, and the Certificate Holder keeps another copy readily available to the Society’s audit team.
  • Change control: Program changes requiring Manual revisions must be submitted to the Society for acceptance and implemented within 90 days of notification of acceptance. Organizational changes affecting compliance require prior Society approval.
  • Exclusive use: The Certificate, issued to a specific location, authorizes a defined scope of work; the Holder must not permit any other party to use the Certificate or OCS Stamp issued to it.
⚠️ The Certificate and the OCS Symbol are at all times the property of the Society. They must be promptly returned upon demand or if the Holder discontinues work covered by the Certificate’s scope.

3. Evaluation, Audits, and Certificate Renewal 🔍

The Quality Assurance Program is evaluated at the initial survey, at each Society audit, and at each renewal survey. The three evaluation forms differ in depth and purpose:

Evaluation Form Content Trigger
Initial Survey Evaluation and acceptance of the QA Manual, plus a survey of Program implementation First application for certification
Society Audit Audit of selected elements of the accepted Program Ongoing post-certification audit program
Renewal Survey Survey of implementation of the accepted Program Certificate renewal

If the Program is not in compliance, corrective action must be taken or the Society may withdraw or refuse to issue a Certificate of Authorization. The Holder must apply for renewal six months before the Certificate’s expiration date; late applications with incomplete documentation may cause loss of accreditation until reaccreditation procedures are completed.

🚨 Apply for renewal at least six months before expiry with complete documentation. If the Certificate lapses, the organization may not continue to act as an authorized SPPE Certificate Holder within the certified scope.

4. Status Identification and Nonconformance Control 🛠️

OE-4215, revised in this addenda, addresses inspection, test, and operating status: the status of inspection and testing must be indicated on the parts where practical, or in records traceable to the parts, to assure required inspections and tests have been performed. Parts that have satisfactorily passed required inspections and tests must be identified. The authority for applying and removing status indicators must be defined, and controls such as tagging, keepers, and seals assist the Operator in proper installation and use of parts/SPPE.

Application of the OCS Symbol must be controlled by written procedures that assure its use only on SPPE meeting this Standard, and the procedure must identify the organizational position responsible and accountable for applying the Symbol. Nonconforming materials, parts/SPPE, services, or activities must be controlled to assure proper disposition and prevent inadvertent use — through identification, documentation, evaluation, segregation where practical, disposition, and notification of affected organizations. Nonconforming materials may be upgraded when conditions permit.

  • 🔍 Traceability: status indicators and records must be traceable to individual parts — a key audit focus.
  • 🔧 Operator protection: tagging, keepers, and seals directly support correct field installation.
  • 📊 Upgrading: upgrading a nonconformance requires evaluation and satisfaction of original requirements, not simple waiver.

5. Frequently Asked Questions ❓

❓ Q: Is SPPE 1A-1991 a standalone standard?
A: No. It is the first Addenda to SPPE-1-1991; revisions are incorporated into the base document as replacement pages and must be used together with the base standard.
❓ Q: What is the purpose of the OCS Symbol?
A: The OCS Symbol marks parts/SPPE that meet the requirements of SPPE-1, attesting that manufacture and QA processes comply. Its application must be controlled by written procedures and is limited to authorized Certificate Holders.
❓ Q: How quickly must an approved Program change be implemented?
A: Changes requiring Manual revisions must be submitted to the Society for acceptance and implemented within 90 days of notification of acceptance; organizational changes affecting compliance require prior approval.
🔍 Q: Why were Appendix I referenced standards revised?
A: Appendix I lists standards such as API 14B (subsurface safety valve systems) and API 14D (surface and underwater safety valves). The addenda synchronizes the listing with current API editions so referenced versions remain valid.