🔬 ASME CRTD-81-2006 is an ASME research report prepared by the Sampling and Monitoring Task Group and the Water Technology Subcommittee of the ASME Research and Technology Committee on Water and Steam in Thermal Systems. It provides consensus recommendations for the sampling and monitoring of feedwater and boiler water chemistry in industrial, utility, and heat-recovery steam generation facilities. The report stresses that all units and sub-systems in the power train must be adequately sampled and monitored: besides the obvious effects of failing to maintain design production of treated water and steam on plant production costs, inadequate monitoring can cause failure of major system components and unplanned outages. It is a companion to the ASME consensus documents on feedwater and boiler water chemistry control, the practical guide to avoiding steam purity problems, and the combined-cycle/cogeneration water and steam chemistry consensus.
The report opens by stressing why effective monitoring matters: without it, chemistry deviations go unnoticed until scaling, corrosion, and carryover accumulate into major equipment failures. The objectives of monitoring are to detect abnormalities early, evaluate treatment effectiveness, and guide operational adjustments. The monitoring scheme should match the plant type (industrial, utility, or heat-recovery boiler), the makeup-water treatment (softened or high-purity), and historical water-quality records.
The report discusses a broad set of parameters: pH, conductivity, dissolved oxygen, hardness, phosphate, alkalinity, silica, iron, copper, suspended solids, dissolved solids, and sodium (for carryover and steam-purity assessment). Parameter selection depends on boiler type, operating pressure, and the treatment program; online instruments and laboratory analyses complement each other to form a complete monitoring system.
Sampling-system design is central to the report. Recommended sample point locations are presented for both softened-water and high-purity makeup systems, covering makeup water, deaerator outlet feedwater, boiler water, and saturated and superheated steam. The report also gives sampling nozzle installation requirements: nozzles should be installed where main-line velocity is high enough to ensure the sample velocity matches the mainstream, avoiding dead zones that would make the sample unrepresentative.
| Sample Location | Purpose | Installation Key Points |
|---|---|---|
| Makeup water (post-treatment) | Monitor incoming quality, evaluate pretreatment | Locate at pretreatment outlet, away from mixing dead zones |
| Deaerator outlet feedwater | Monitor dissolved oxygen, pH, hardness, etc. | Install nozzle perpendicular or 45° facing the flow |
| Boiler water | Assess internal chemistry regime and concentration cycles | Sample both steam space and water space of the drum for comparison |
| Saturated / superheated steam | Monitor steam purity and carryover | Extend nozzle into the mainstream; prevent wall water-film contamination |
| Condensate (as applicable) | Detect condenser leakage and contaminant ingress | Choose points per system configuration |
Table 3 of the report provides the minimum purge times required for representative sampling of water. Because water retained in the sample line may differ from the mainstream (especially after shutdown, flushing, or load changes), the line must be thoroughly purged before sampling to expel the stagnant water. The purge time depends on line length, internal diameter, flow rate, and sampling-system configuration.
Tables 1 and 2 give sampling frequency guidelines by location and test for sodium-zeolite (softened) makeup and high-purity makeup systems respectively; Table 4 summarizes the corresponding test methods. The general principle: critical parameters (feedwater dissolved oxygen, boiler-water pH) are monitored at high frequency, others are relaxed according to risk and stability, but startup, shutdown, and load disturbances call for intensified monitoring.
| Test Parameter | Softened Makeup | High-Purity Makeup | Typical Method |
|---|---|---|---|
| pH | Per shift / daily | Online continuous or daily | pH meter / colorimetric |
| Conductivity | Daily | Online continuous | Conductivity meter (cation-conductivity where applicable) |
| Dissolved oxygen | Per shift | Per shift / online | Indigo carmine or electrochemical probe |
| Hardness | Per shift | Daily | EDTA titration |
| Phosphate / alkalinity | Daily | Daily | Titration |
| Silica | Weekly | Weekly / daily | Colorimetric / spectrophotometric |