📦 ASME B133.11-1982 is a part of the ASME B133 series of gas turbine procurement standards. It focuses specifically on the complete logistics chain of a gas turbine package: preservation at the factory, boxing and closures, the shipping envelope, transportation, receiving inspection, unloading and storage, depreserving, installation, prestart checks, initial startup, and the punch list. Rather than being a mandatory technical regulation, the Standard is intended to provide the user with a review of items that should be considered when preparing procurement specifications. Because manufacturers legitimately use a variety of methods to achieve the same installation and startup results, the user is advised to consult the manufacturer on the use and interpretation of the Standard and to embed the agreed requirements in the more detailed site specifications.
The Standard comprises twelve sections: Scope; Preservation; Boxing; Closures; Shipping Envelope; Transportation; Receiving Inspection, Unloading, and Storage; Depreserving; Installation; Prestart Checks; Initial Startup; and Punch List. It applies to open-cycle, closed-cycle, and semi-closed-cycle gas turbines with conventional combustion systems for industrial, marine, and electric power applications, together with the auxiliaries needed for proper operation. Gas turbines applied to earth-moving machines, agricultural and industrial tractors, automobiles, trucks, buses, and aero-propulsion units are excluded. For turbines using unconventional heat sources such as chemical processes, nuclear reactors, or furnaces for supercharged boilers, the B133 standards may be used as a basis with appropriate modifications.
Preservation is the first line of defense against corrosion, moisture ingress, and degradation during storage and transit. The Standard sets preservation duration by shipment class as shown below:
| Shipment Class | Required Preservation Duration | Remarks |
|---|---|---|
| Domestic shipments | ≥ 3 months (outdoor storage plus transit time) | Planned inspection, renewal, or replacement of preservation materials is not precluded |
| Export shipments | ≥ 1 year (storage plus transit time) | Air-transportable items may meet the domestic 3-month minimum |
| Extended preplanned storage | Beyond 1 year, or as agreed | Requires special preservative selection, inspection, and renewal planning |
Three types of preservative treatment are recognized. Direct application types are applied to metal surfaces, principally machined surfaces, such as paints, greases, sprays, and cocooning; they must be selected for the climate and duration of the planned shipment class, and treated surfaces must be protected from abrasion or accidental impact. Area treatment types address large enclosed spaces, such as vapor phase inhibitors, chemical or mechanical moisture controllers, and gases; they must not damage the equipment during prolonged exposure, and visual indicators should be provided to verify adequacy. Additive types are added to fluids for shipment and storage, such as corrosion inhibitors, anti-freeze, or oils, and require clear placards on the packaging.
The sections on boxing and closures require that crates and cases withstand the expected stacking, lifting, and vibration loads; that openings such as flanges, pipe connections, and bearing housings be closed with moisture-proof covers or closures to exclude foreign matter and humidity; and that the shipping envelope — outer dimensions, center of gravity, and lifting points — be compatible with the selected transport mode (road, rail, sea, or air) and clearly marked with lifting points, center of gravity, and warning signs.
The transportation section calls for defining the mode and the responsible party, specifying impact limits and permissible tilting during handling, and, where required, installing shock recorders so that handling conditions can be verified after arrival.
On arrival, the Standard directs the following sequence of activities:
The installation section addresses foundations and anchor bolts, alignment, piping connections, electrical and instrumentation wiring, and the integrated commissioning of auxiliary systems. Prestart checks should cover:
Initial startup follows the manufacturer’s prescribed sequence of cold crank, ignition, acceleration, warm-up, synchronization, and loading, with any anomalies recorded and resolved. Finally, a punch list is compiled to track outstanding items and defect rectification to closure, forming the basis for formal handover and the start of the warranty period.