⚡ BS EN 61083 is the British Standard adopting, identically, the IEC 61083 European standard series for requirements for instruments and software used in high-voltage and high-current tests. Developed by IEC/TC 42 (High-voltage testing techniques), approved by CENELEC as EN 61083, and adopted in the UK by committee PEL/42, it specifies requirements for measuring instruments and software in high-voltage testing (e.g. lightning impulse tests, switching impulse tests, d.c./a.c. withstand tests) used to verify insulation performance and equipment withstand capability. The accuracy and reliability of measurement data directly affect the test conclusion. This batch includes Part 1 (instruments for impulse voltage tests, 2001 edition) and Part 2 (software for tests with impulse voltages and currents, 2013 edition).
💡 Impulse voltage/current waveforms are extremely short (microsecond level) and of very high amplitude (up to MV/kA); their measurement relies on high-bandwidth digital recorders and dedicated software. BS EN 61083 sets systematic requirements and verification for instruments and software, ensuring trustworthy test data.
1. Scope and General Framework 📌
The BS EN 61083 series applies to measuring instruments and software used in high-voltage and high-current tests. The series structure is:
- Part 1: Requirements for instruments for impulse voltage tests: performance requirements and test methods for digital recorders/measurement systems (oscilloscopes, digitisers, etc.) used for impulse voltage tests.
- Part 2: Requirements for software for tests with impulse voltages and currents: requirements and verification methods for software used to evaluate impulse voltage and current test data (e.g. waveform parameter calculation).
ICS classification is 17.220.20 / 19.080. BS EN 61083-1:2001 corresponds to IEC 61083-1:2001 (superseding the 1993 edition); BS EN 61083-2:2013 corresponds to IEC 61083-2:2013 (superseding the 1997 edition).
⚠️ Division of labour between Part 1 and Part 2: Part 1 sets requirements for the “hardware” (measuring instruments), while Part 2 sets requirements for the “software” (data processing and waveform evaluation); together they make the complete measurement chain from acquisition to evaluation trustworthy.
2. Series Composition and Technical Points 🔧
| Standard | Title | Focus | IEC Equivalent | Status |
| BS EN 61083-1:2001 | Requirements for instruments for impulse voltage tests | Digital recorders, measurement system performance and tests | IEC 61083-1:2001 | Current (supersedes 1993) |
| BS EN 61083-2:2013 | Requirements for software for tests with impulse voltages and currents | Waveform evaluation software requirements and verification | IEC 61083-2:2013 | Current (supersedes 1997) |
1. Instruments for Impulse Voltage Tests (Part 1)
Part 1 specifies requirements for measuring instruments for impulse voltage tests:
- Recorder performance: sampling rate, bandwidth, resolution, and record length of digital recorders (digital oscilloscopes/transient recorders).
- Measurement system requirements: overall performance and calibration of the divider, converter, and recording system.
- Performance tests: test methods for amplitude accuracy, time-parameter measurement accuracy, and linearity.
- Environment and EMC: stable operation under the strong electromagnetic interference of the test environment.
2. Software for Impulse Tests (Part 2)
Part 2 specifies requirements for software used in impulse voltage and current tests (2013 edition):
- Software functions: calculation of waveform parameters (peak, time parameters, overshoot, etc.), curve fitting, and reporting.
- Algorithm requirements: accuracy of the algorithms (e.g. polynomial fitting, interpolation) used to calculate impulse parameters.
- Software verification: verification that software output agrees with standard calculation methods using reference data.
- Documentation and traceability: documentation of software version, configuration, and verification records.
💡 The calculation of impulse parameters (e.g. front time, time-to-half-value, overshoot) is highly sensitive to software algorithms: different fitting/interpolation methods can produce differences; Part 2’s verification requirements ensure comparable results across different software.
3. Key Technical Requirements 🔬
Key technical requirements for high-voltage impulse test measurement systems include:
- Amplitude and time-parameter accuracy: measurement uncertainty of peak voltage and front/time-to-half-value parameters should meet requirements.
- Bandwidth and sampling rate: the recorder should have sufficient bandwidth and sampling rate to capture nanosecond/microsecond impulse waveforms without distortion.
- Linearity and dynamic range: remain linear and accurate over the entire measurement range.
- Interference immunity: stable measurement under the strong electromagnetic interference produced by impulse tests.
- Software algorithm correctness: waveform evaluation software should calculate parameters per standard algorithms and be independently verified.
🚨 High-voltage impulse testing is hazardous: set safety fences and interlocks in the test area, confirm residual charge is discharged after a flashover before entering, and ensure the measurement system is reliably earthed and isolated from test voltage to prevent personal injury and equipment damage.
4. Engineering Practice and Application 🛠️
- 🔍 Selection: choose digital recorders and dividers meeting the bandwidth/sampling-rate requirements and conforming to BS EN 61083 for the test voltage level and waveform.
- 🔧 Setup: form a complete measurement chain with the measurement system, trigger/synchronisation, software, and computer, and calibrate per the standard.
- 📊 Test execution: conduct impulse tests per the IEC 60060 series, recording and evaluating waveforms with instruments and software meeting BS EN 61083 requirements.
- 📋 Recording and reporting: save waveform data, software version, and verification records, and produce a complete test report.
5. Frequently Asked Questions ❓
❓ Q: What is the relationship between Part 1 and Part 2?
A: Part 1 specifies requirements for measuring instruments (hardware) for impulse voltage tests, and Part 2 specifies requirements for software (data processing) for impulse voltage and current tests; together they form the complete measurement chain from signal acquisition to parameter evaluation.
⚡ Q: Why do recorders need high bandwidth and high sampling rate?
A: Impulse waveforms last microseconds or even sub-microseconds; if bandwidth or sampling rate is insufficient, the waveform is distorted, leading to errors in peak and time-parameter calculation, so sampling must be fast enough.
📊 Q: What is the significance of software verification?
A: Impulse parameter calculation depends on algorithms, and different implementations may differ; verification against standard reference data ensures software output agrees with the specified method, ensuring comparability and reliability of test results.
🔌 Q: What are the key safety points in testing?
A: Set safety fences and interlocks, earth reliably, confirm no residual charge after discharge, and ensure personnel are trained and operate per procedure, preventing high-voltage electric shock and equipment damage.